1 Answers
Difference between Work Breakdown Structure (WBS) and Network in SAP Project System
In SAP Project System, the Work Breakdown Structure (WBS) and Network are two important components used for project planning and tracking. Here are the key differences between them:
Work Breakdown Structure (WBS)
- Organizes project work into a hierarchical structure
- Breaks down project deliverables into smaller, manageable components
- Helps in assigning responsibilities to project team members
- Provides a visual representation of project tasks and their relationships
Network
- Defines the sequence of activities in a project
- Shows the dependencies between project activities
- Helps in determining the critical path of the project
- Used for scheduling and resource allocation
Overall, the WBS focuses on organizing project deliverables, while the network focuses on sequencing and scheduling project activities in SAP Project System.
Please login or Register to submit your answer