Can you explain the difference between standard and network activities in SAP PS?

1 Answers
Answered by suresh

Standard Activities in SAP PS:

Standard activities in SAP PS are predefined work activities that are common across different projects. These activities are created once and can be reused in multiple projects without having to recreate them each time. Standard activities help in standardizing project planning and execution, saving time and effort by avoiding duplication of work.

Network Activities in SAP PS:

Network activities in SAP PS are specific work activities that are unique to a particular project. These activities are created within a project network and are interconnected to form the project's overall work breakdown structure. Network activities are essential for defining the sequence of tasks, dependencies, and resources required for completing a project successfully.

In summary, the main difference between standard and network activities in SAP PS is that standard activities are generic and reusable across projects, while network activities are project-specific and form the core of the project's execution plan.

Answer for Question: Can you explain the difference between standard and network activities in SAP PS?