Work Breakdown Structure (WBS) vs Network in SAP PS
In SAP Project System (PS), both the Work Breakdown Structure (WBS) and Network play important roles in project management. Here is the key difference between the two:
Work Breakdown Structure (WBS)
The Work Breakdown Structure (WBS) is a hierarchical structure that breaks down a project into smaller, manageable components. It represents the project's deliverables and organizes the work into manageable sections. Each level of the WBS represents a different level of detail in the project hierarchy.
Network
On the other hand, the Network in SAP PS is a graphical representation of the project's activities and their dependencies. It shows the sequence in which activities need to be completed and the relationships between them. The network helps in identifying the critical path of the project and determining the overall project timeline.
Key Differences:
- WBS is a hierarchical structure that breaks down the project deliverables, while the network shows the sequence of project activities.
- WBS focuses on organizing work packages, while the network emphasizes activity scheduling and dependencies.
Both the WBS and Network are essential tools in SAP PS that help in efficient project planning, tracking, and control.